Our Recent Projects
Testing of 30 x LV Schneider circuit breakers:
-
Perform secondary injection testing of LV circuit breaker protection relays.
Test and commission 6 x 11kV Ring Main Units:
-
Secondary injection testing of protection relays and primary injection of CT’s.
-
Check functionality of switchgear.

Upgrade electrical metering, Perth WA – June/July 2016.
Meter calibration, installation and testing:
-
Check accuracy of electrical meters.
-
Move, reinstall and test meters.
Test and commission 22kV RMU (Ring Main Units):
-
Program relay settings.
-
Carry out primary and secondary injection testing of protection relays and CT’s.
Test and commission 22kV transformers:
-
Winding Resistance and Turns Ratio.
-
IR (Insulation Resistance) and PI (Polarisation Index).